Building a Landscape-Based Early Warning System in Santong–Murus Malang

 

The Santong–Murus Malang Landscape faces various risks associated with changing weather patterns and environmental conditions. Heavy rainfall can increase the risk of floods and landslides, while prolonged dry periods can affect water availability and community activities. These conditions make timely information on weather and environmental changes essential. However, early warning information needs to be translated into clear actions so that communities can reduce risks when extreme conditions occur.

In response to this need, Yayasan SHEEP Indonesia, in collaboration with BMKG NTB, conducted a Dissemination and Consultation Meeting on the Draft Standard Operating Procedures (SOP) for Early Warning of Extreme Wet and Dry Weather in the Santong–Murus Malang Landscape.

The activity involved 28 participants from 14 villages, including members of the Landscape-Based Early Warning Working Group in Santong–Murus Malang, representing village governments, community members, and volunteer groups. Representatives from FPRB, RAPI North Lombok Regency, and KENCANA Kayangan and Bayan also participated in the activity.

The activity provided a shared space to review the SOP development process and ensure that the proposed early warning mechanism could be implemented in real-life situations. Participants discussed the progress of the SOP development and provided input on the monitoring process, receipt of information, dissemination of warnings, determination of hazard levels, and anticipatory actions that communities need to take.

“Early warning is not only about how we receive weather information, but also about how that information reaches communities and is translated into action before impacts occur. Therefore, this SOP needs to be developed based on the conditions and experiences of communities in the Santong–Murus Malang Landscape,” said M. Zainur, Chair of the Landscape-Based Early Warning Working Group, during the activity.

The development of the SOP considered the specific risk characteristics of the Santong–Murus Malang Landscape. Participants discussed the history of disasters, weather and climate information, water resource conditions, forest areas, agricultural areas, settlements, and community vulnerabilities. For example, during extreme wet weather in the Murus Malang Landscape, water may stop flowing when pipes are damaged by landslides.

This information was then used to identify indicators that could serve as early signs for communities when weather conditions begin to pose a risk.

During the consultation, participants also discussed the relationship between information from official sources, such as BMKG, and community observations at the local level. Weather forecasts, early warnings of heavy rainfall, seasonal outlooks, and drought-related information from BMKG will be received by the Early Warning Working Group. The information will then be forwarded to the Village Information and Data System (SID) for dissemination through village government and community WhatsApp groups, public announcement systems, traditional bamboo slit drums, communication radios, or other appropriate channels.

Defining roles among different actors was an important part of the SOP development process. Village governments will play a role in coordination, decision-making, and communicating information to communities. Volunteer groups and the Early Warning Working Group will be responsible for monitoring conditions, receiving and forwarding information, and supporting the dissemination of warnings.

The discussion also identified several challenges that could affect the implementation of the early warning system, including limited access to information, different understandings of hazard levels, limited communication facilities, and unclear roles and actions at each warning level.

Participants then provided input on the draft SOP, particularly regarding the determination of indicators and hazard levels, communication and information dissemination channels, the division of roles among actors, and the types of early action that communities can realistically undertake.

The input from the consultation process will be used to improve the draft SOP before it enters the finalization stage.

The process also demonstrated that an effective early warning system requires a clear connection between information, actors, communication, and action. Weather information needs to reach the right people, be communicated through channels that communities understand and trust, and be followed by actions that have been agreed upon in advance.

“Early warnings should not rely solely on information from BMKG. Communities also need to monitor conditions using traditional methods and local knowledge passed down by previous generations. This activity is part of our effort to adapt to the increasingly visible impacts of climate change,” said Fauzi, Area Manager for Lombok at Yayasan SHEEP Indonesia.

Following the consultation, the stakeholders agreed on the next steps, including the completion of the Early Warning SOP document. The SOP is planned to be tested through a Tabletop Exercise (TTX) and simulation.